The total area of the shaded region is solved to be 154.93 cm²
How to find the total area of the shaded regionThe diameter is solved using Pythagoras theorem given by the the formula
hypotenuse² = opposite² + adjacent²
plugging the values as in the problem
let x be the required distance
x² = 8² + 15²
x² = 289
x = √289
x = 17
Work out the area of the triangle using the formula
= 1/2 * base * height
base = hypotenuse or diameter
height = radius = diameter/2
= 0.5 * 17 * 8.5
= 72.25 cm²
Area of the circle
= Π * radius²
= 22/7 * 8.5²
= 226.98 cm²
shaded portion
= Area of the circle - area of the triangle
= 226.98 - 72.25
= 154.93 cm²
the area of the shaded portion is 154.93 cm²
Learn more on area of shaded portion here:
https://brainly.com/question/27947205
#SPJ1
The registration fee for a used car is 0.6% of the sale price of $6,300. How much is the fee?
Answer: 37.80
Step-by-step explanation:
Which system of equations can be represented by this matrix?
Answer:
answer is c
Step-by-step explanation:
I learned matrix
find an equation of the tangent line to the graph of y = e−x2 at the point 2, 1 e4 .
Expand (1 + √2)(3-√2)
Answer: 1⋅3+1(−√2)+√2⋅3+√2(−√2)
Step-by-step explanation:
The number 651 is what percent of 700?
Answer:
93%
Step-by-step explanation:
651/700
Answer: 93%
Step-by-step explanation:= (
(651 × 100/700) × 1/100 = 93/100
PLSSS HELP ASAP 30PTS
Consider parallelogram ABCD with vertices A(-6, 6), B(0, 10), C(2,4), and D(-4, 0). Classify the parallelogram and select ALL that apply.
MORE THAN ONE POSSIBLE ANSWER
The figure is neither a rhombus nor a rectangle since the sides are of varied lengths and are not at right angles. "None of the other" applies.
Given that,
Consider parallelogram ABCD with vertices A(-6,6), B(0,10), C(2,4) and D(-4,0).
We have to find the parallelogram is square, rectangle, rhombus and none of the above.
We know that,
In the attached figure, which shows the number of grid squares for each side, we can see that one side is the diagonal of a 23 rectangle and the other side is the diagonal of a 13 rectangle. This reveals two things to you: The sides are not at perfect angles to one another and are of varied lengths. The slopes of the segments would be opposing reciprocals (if the sides were perpendicular).
Therefore, The figure is neither a rhombus nor a rectangle since the sides are of varied lengths and are not at right angles. "None of the other" applies.
To learn more about rectangle visit: https://brainly.com/question/15019502
#SPJ1
what is one plus 59 plus 666662
Answer:
66,726
Step-by-step explanation:
Answer:
666,722
Step-by-step explanation:
1 + 59 + 666,662
= 60 + 666,662
= 666,722
i hope this helped
Select all of the equations below that are equivalent to:
17 - k = 52
Use properties of equality.
Answer:
there are no equations below...
Step-by-step explanation:
Can you name the angle pairs and type the correct code? Please remember to type in ALL CAPS with no spaces.
Answer:
AGDB
Step-by-step explanation:
Pair 1: Alternate interior
Pair 2: Alternate exterior
Pair 3: Same-side interior
Pair 4: Same-side exterior
The sides of a triangle are 10 cm, 8 cm, and 10 cm. Classify the triangle.
If two sides of the triangle is congruent then the triangle is known as isosceles triangle.
What is the triangle?The polygonal shape of a triangle has a number of sides and three independent variables. Angles in the triangle add up to 180 °.
The two triangular legs and their opposing angles are congruent in an isosceles triangle.
In the given triangle, the sides of a triangle are 10 cm, 8 cm, and 10 cm.
In the triangle, the two sides of the triangle are congruent.
If two sides of the triangle is congruent then the triangle is known as isosceles triangle.
More about the triangle link is given below.
https://brainly.com/question/25813512
#SPJ1
Which is a survey?
a study that collects data on every subject in a sample
the data collected from a population
the questions used for a sample
the questions used for a population
how do i find the answer
The value of the angles of the given quadrilateral are;
8) ∠X = 124° = ∠W
∠Y = 56° = ∠Z
9) ∠J = 44° = ∠K
∠L = 136° = ∠M
How to find the angles of a quadrilateral?The sum of angles of a quadrilateral is equal to 180 degrees. Now, in the quadrilateral given, the two angles on the slant side always equal 180 degrees. Thus;
8) From the given trapezium, we can use the definition above to say that;
∠X + ∠Y = 180°
Thus;
(13x - 7)° + (8x - 2)° = 180°
21x - 9 = 180
21x = 189
x = 189/21
x = 9
Thus;
∠X = (13(9) - 7)°
∠X = 124° = ∠W
∠Y = 180° - 124°
∠Y = 56° = ∠Z
9) From the above, we can apply the same to this quadrilateral to get;
7x + 2 + 25x - 14 = 180
32x - 12 = 180
32x = 180 + 12
32x = 192
x = 192/32
x = 6
∠J = (7(6) + 2)
∠J = 44° = ∠K
∠L = 180 - 44
∠L = 136° = ∠M
Read more about Angles of a quadrilateral at; https://brainly.com/question/16941531
#SPJ1
You manage a staff of 9 employees. Each employee has equally done an excellent job this year. If upper management has allotted a bonus for your department of $30,000, what dollar bonus amount would each employee get if divided equally (round to nearest dollar)?.
The amount that each employee will get out of the bonus to your department will be $3,000.
What will each employee get?
You manage a staff of 9 employees in your department which means that there are 10 people in total.
The amount that each person will get from the bonus will therefore be:
= 30,000 / 10 employees
= $3,000
Find out more on bonuses at brainly.com/question/933169.
#SPJ4
Sharon started with $42 in her bank account and
added $16 per week. Neil started out $70 in debt and deposited $30 per week. Determine how many weeks it will take them to have saved the same amount of money.
Answer:
8 weeks
Step-by-step explanation:
The two equations I got from this are y=16x+42 and y=-70+30x
I graphed both equations online to see what the intersection would be the intersection between both equations is (8,170). I think that this means that in 8 weeks they would both be at 170 dollars, so I think that it will take them 8 weeks to have the same amount of money saved
(if wrong, im sorry..)
The number of weeks it will take them to have saved the same amount of money will be 8.
What is a linear equation?A connection between a number of variables results in a linear model when a graph is displayed. The variable will have a degree of one.
The linear equation is given as,
y = mx + c
Where m is the slope of the line and c is the y-intercept of the line.
Sharon began with $42 in her financial balance and added $16 each week. Neil began $70 underwater and kept $30 each week.
Let 'x' be the number of weeks and 'y' be the total amount. Then the equations are given as,
y = 16x + 42 ...1
y = 30x - 70 ...2
From equations 1 and 2, then we have
30x - 70 = 16x + 42
14x = 112
x = 8
The number of weeks it will take them to have saved a similar measure of cash will be 8.
More about the linear equation link is given below.
https://brainly.com/question/11897796
#SPJ2
Complete the equation describing how
x and y are related.
Answer: y = 1x+4
the related between the x and y is x plus one and y plus 4
Step-by-step explanation:
The sum of three consecutive integers is 42. Which of the equations could represent this relationship? Select the two correct answers. x + (x + 1) + (x + 2) = 42 x + (x + 2) + (x + 4) = 42 (x minus 1) + x + (x + 1) = 42 (x minus 2) + x + (x + 2) = 42 x + 2 x + 3 x = 42
The two equations that can represent the relationship is
i. x +( x+1) + (x+2) = 42 and
Ii. (x-1) +x + (x+1) = 42 ( option A and C)
What are consecutive integers?Consecutive integers are those numbers that follow each other. They follow in a sequence or in order. For example, a set of natural numbers are consecutive integers.
For example, 4,5,6,7 are consecutive integers. This means that the difference between two consecutive numbers is 1.
If the first number is x, then the second number is (x+1 ) and the third number is (x+3)
The sum of the three number is x +( x+1) + (x+2) = 42
if the second number is x, then the first number is (x-1) and the third number is x+1
Therefore the sum of the three numbers can also be written as (x-1) +x + (x+1) = 42
learn more about consecutive numbers from
https://brainly.com/question/28669351
#SPJ1
-3x²+x+ 5 = 0
A.-3+ 24
6
B.-5+√8
2
C.-1+√61
-6
D. 3+√12
10
K
Answer:
c is your answer
Step-by-step explanation:
x = 1 +_ √61/6
-1 1/6 divided by 1/4=
Pls help me
Answer:
-14/3 or -4.67
Step-by-step explanation:
division.
A concrete drain is 10m long, with an outside diameter of 1m and an inside diameter of 0.8m. Determine the volume of the concrete required to make the drain, to the nearest tenth of a cubic metre
Answer: To calculate the volume of the concrete required to make the drain, we need to find the volume of the cylinder formed by the outside diameter of the drain and subtract the volume of the cylinder formed by the inside diameter of the drain.
The formula for the volume of a cylinder is:
V = πr^2h
where V is the volume, r is the radius of the base of the cylinder, and h is the height of the cylinder.
The radius of the base of the outside cylinder is 0.5m (the diameter of 1m divided by 2) and the height is 10m. The radius of the base of the inside cylinder is 0.4m (the diameter of 0.8m divided by 2) and the height is also 10m.
So the volume of the outside cylinder is:
V = π * 0.5^2 * 10 = 15.7 m^3
and the volume of the inside cylinder is:
V = π * 0.4^2 * 10 = 12.6 m^3
To find the volume of the concrete required to make the drain, we subtract the volume of the inside cylinder from the volume of the outside cylinder:
15.7 m^3 - 12.6 m^3 = 3.1 m^3
So the volume of concrete required to make the drain is approximately 3.1 cubic metres. To the nearest tenth of a cubic metre, this is 3.1 m^3.
Is the line through points P(8, 4) and Q(6, –1) parallel to the line through points R(1, –4) and S(4, 5)? Explain.
Answer:
No, the lines are not parallel
Step-by-step explanation:
They are not parallel because the slopes of the lines are not equal.
I WILL GIVE BRAINLIEST TO THE CORRECT PERSON AFTER 2 PEOPLE ANSWERRRR
Answer:
x=42
Step-by-step explanation:
Figure A has been scaled by 2/7, so we know that[tex]x * 2/7 = 12.[/tex] Multiplying both sides by 7 gives us [tex]2x = 84[/tex]. Dividing both sides by 2 gives us that x = 42. This is our answer.
Answer: 42
Step-by-step explanation:
2/7x=12
x = 12 * 7/2
x=84/2
x=42
Find the nth term of this quadratic sequence
2, 8, 18, 32, 50, ...
The nth term of the given quadratic sequence is 2n².
What is quadratic sequence?
The ordered sets of numbers known as quadratic sequences are based on the rule n^2 = 1, 4, 9, 16, 25,.... (the square numbers). Every quadratic sequence has a n^2 term.
Consider, the given quadratic sequence
2, 8, 18, 32, 50, ...
we have to find nth term of this quadratic sequence ; 2 , 8 , 18 , 32, 50, ...
To find the nth term, we have to find the relation between the given terms.
here we see,
1st term = 2 = 2 × 1 × 1 = 2 × 1²
2nd term = 8 = 2 × 2 × 2 = 2 × 2²
3rd term = 18 = 2 × 3 × 3 = 2 × 3²
4th term = 32 = 2 × 4 × 4 = 2 × 4²
similarly 5th term = 2 × 5² = 2 × 25 = 100
...........
so nth term = 2 × n² = 2n²
Hence, the nth term of the given quadratic sequence is 2n².
To know more about quadratic sequence, click on the link
https://brainly.com/question/29721348
#SPJ1
A regular polygon has its exterior angles all equal to 5⁰ Find the number of sides of the polygon.
calculate the size of the exterior and interior angles of all the different polygon.
Show how u got all the answers
Solve for y
1. -2y + 7 = -5
Solve for x
2. -3(x + 5 = -9
3. X+(/2.5= -7.79
Solve for n
4. 3.33 + 2n = -7
Answer: 1. y = 6
2. x = -2
3. X = -10.29
4. n = -5.165
Step-by-step explanation:
1. -2y + 7 = -5
-2y + 7 - 7 = -5 - 7
-2y = -12
y = 6
2.-3(x + 5) = -9
3(x+5) = 9
x+5 = 3
x = 3 - 5
x = -2
3. X+2.5= -7.79
X= -7.79 - 2.50
X = -10.29
4. 3.33 + 2n = -7
3.33 - 3.33 + 2n = -7 - 3.33
2n = -10.33
n = -5.165
Find the midpoint of the segment with the following endpoints
(5,5) and (1,1)
The midpoint of the segment given (5,5) and (1,1) is (3, 3).
What is midpoint?In geometry, the midpoint is the middle point of a line segment. It is equidistant from both endpoints, and it is the centroid both of the segment and of the endpoints. It bisects the segment.
Coordinates of the midpoint of the line joining the points (x₁,y₁) and (x₂,y₂)= [(x₁ + x₂)/2 , (y₁ + y₂)/2].
The midpoint of the line segment with endpoints (5,5) and (1,1)
= [ ( 5 + (1))/2 , ((5) + 1)/2 ]
= [ (6)/2 , 6/2 ]
= [ 3, 3
Therefore, the midpoint of the line segment with endpoints is (3, 3).
Learn more about the midpoint at: https://brainly.com/question/12223533
#SPJ1
Brainliest + ten points to first correct answer! word problem
The project manager for the state department of highways has two beds for the resurfacing of a 10 mile stretch of highway. The first company gives a bit of $120,000 per mile and will guarantee the web for eight years. The second company bids the word for $150,000 per mile using a new asphalt material made from used tires. The second company will guarantee the work for 12 years. Determine the price per mile per year for each company and decide which company should get the contract based on the least expensive price per mile per year.The project manager for the state department of highways has two beds for the resurfacing of a 10 mile stretch of highway. The first company gives a bit of $120,000 per mile and will guarantee the web for eight years. The second company bids the word for $150,000 per mile using a new asphalt material made from used tires. The second company will guarantee the work for 12 years. Determine the price per mile per year for each company and decide which company should get the contract based on the least expensive price per mile per year
Answer:
The second company should get the contract.
Question
The project manager for the state department of highways has two beds for the resurfacing of a 10 mile stretch of highway.
Reason
Based on the least expensive price per mile per year, the second company should get the contract. This is because the price per mile per year for the second company is lower than the price per mile per year for the first company.
The first company gives a bit of $120,000 per mile and will guarantee the web for eight years. The second company bids the word for $150,000 per mile using a new asphalt material made from used tires.
The second company will guarantee the work for 12 years. Determine the price per mile per year for each company and decide which company should get the contract based on the least expensive price per mile per year.
The project manager for the state department of highways has two beds for the resurfacing of a 10 mile stretch of highway. The first company gives a bit of $120,000 per mile and will guarantee the web for eight years.
The second company bids the word for $150,000 per mile using a new asphalt material made from used tires. The second company will guarantee the work for 12 years.
Determine the price per mile per year for each company and decide which company should get the contract based on the least expensive price per mile per year
50 POINTS IF ANSWERED PLS!!!!!
triangle ABC is an isosceles triangle. find the missing angles and side measures.
Angle A = 40 degrees
Angle C = 70 degrees
Side AC = 12 cm
2X-Y=4
x=4-y
please explain each step
Step-by-step explanation:
2X-Y=4 ---------(1)
x=4-y---------(2)
since x = 4 – y just substitute for eqn 1
2(4–y) – y = 4
8 – 2y –y=4
8 –3y = 4
–3y=4–8
–3y=–4
y=–4/–3
y= 4/3
since y = 4/3 just substitute for y in eqn (2)
x=4–4/3
multiply both sides by 3
3x=12–4
3x=8
x=8/3 or 2 2/3
Here are summary statistics for the weights of Pepsi in randomly selected cans: n = 36, x-bar = 0.82407, s = 0.00567. Use a confidence level of 95% to complete parts (a) through (d) below.
A) Identify the critical value t a/2 used for finding the margin of error.
T a/2 =
B) Find the margin of error
The margin of error, a statistic, is a measure of how much random sampling error there is in survey data.
The margin of error exists 0.07728.
What is meant by margin of error?A statistic known as the margin of error describes how much random sampling error there is in survey data. Less faith should be placed in a poll's results representing the outcome of a population census as the margin of error increases.
A survey's margin of error, also known as the confidence interval, is a measurement of error in the data, particularly when the sampling method of a survey is used. This indicator lets researchers know to what extent survey findings should be taken as representative of the entire community under study.
Given : n = 36
x-bar = 0.82407
s = 0.00567
Confidence level 95%
The 2 - critical Valve = 2.03
A) Let the equation be
[tex]$S F=\sqrt{\frac{\bar{x}(1-\bar{n})}{n}}[/tex]
substitute the values in the above equation, we get
[tex]$\Rightarrow \sqrt{\frac{(0.82412)(1-0.82412)}{100}}$$[/tex]
S E = 0.03807
B) Margin of error = (0.03807)(2 × [tex]I_2[/tex])
Margin of error = 0.07728
To learn more about margin of error refer to:
https://brainly.com/question/10218601
#SPJ1
can you solve please